Author Topic: Wow! $728K Change Order on Boulder Bridge Demo  (Read 4907 times)
Wrinkle
Guest
« on: June 08, 2009, 09:20:18 pm »

REF:Public Works Agenda June 9, 2009, Item #9

http://www.tulsacouncil.org/inc/search/meeting_detail.php?id=18OH5S25262009122140

....now that you're as shocked as I was, the good part:
http://www.tulsacouncil.org:8080/SuperContainer/RawData//SCXIMN4G365200915020/09%2D394%2D1.pdf?a=1

...it's a deductive Change Order. That is, savings. What a concept.

Logged
FOTD
Guest
« Reply #1 on: June 08, 2009, 09:35:32 pm »

REF:Public Works Agenda June 9, 2009, Item #9

http://www.tulsacouncil.org/inc/search/meeting_detail.php?id=18OH5S25262009122140

....now that you're as shocked as I was, the good part:
http://www.tulsacouncil.org:8080/SuperContainer/RawData//SCXIMN4G365200915020/09%2D394%2D1.pdf?a=1

...it's a deductive Change Order. That is, savings. What a concept.



Hmmmm....conversion of IDL Fed Funding?
Logged
Wrinkle
Guest
« Reply #2 on: June 09, 2009, 07:10:32 am »

Hmmmm....conversion of IDL Fed Funding?

Now, that would be conspiratorial and require collusion with a contractor, wouldn't it?


Logged
Wrinkle
Guest
« Reply #3 on: June 09, 2009, 08:11:18 am »

I was just recalling an Ordinance or such which states a Change Order can never exceed 25% of the original Contract Amount. Even though this is a reduction, wouldn't the same rule apply?

In this case, the Original Contract Amount is $3,073,989.00

25% would be $768,497.25

....weeeugh, just under the wire.

Their $728,022.50 comes in at 23.68%

But, shown as 0% on the documents (presumably due to it being negative).

Logged
FOTD
Guest
« Reply #4 on: June 09, 2009, 12:05:47 pm »

Even though this is a reduction, wouldn't the same rule apply?


doubtful....

Wonder what's up....pedestrian bridge?
Logged
Vision 2025
Philanthropist
****
Offline Offline

Posts: 851


WWW
« Reply #5 on: June 09, 2009, 01:48:16 pm »

I was just recalling an Ordinance or such which states a Change Order can never exceed 25% of the original Contract Amount. Even though this is a reduction, wouldn't the same rule apply?

In this case, the Original Contract Amount is $3,073,989.00

25% would be $768,497.25

....weeeugh, just under the wire.

Their $728,022.50 comes in at 23.68%



But, shown as 0% on the documents (presumably due to it being negative).



Interesting, wonder why that differs form the State Competitive Bidding Act.

also typically the change order limit is only on additive changes.
Logged

Vision 2025 Program Director - know the facts, www.Vision2025.info
PonderInc
City Dweller
City Father
*****
Offline Offline

Posts: 2460


« Reply #6 on: June 18, 2009, 10:57:57 am »

Perhaps the economy, which has put the kibbosh on construction projects throughout the nation, and the world, has caused the cost of materials to go down?  (It certainly torpedoed the value of recyclable materials...wouldn't it have a similar effect on building materials?)

On the other hand, I also heard that we got fed stimulus money to help pay for the Boulder Bridge.  (Which is good b/c the initial 3rd penny sales tax allotment was about half of that required to demo and rebuild the bridge.)
Logged
Conan71
Recovering Republican
T-Town Elder
******
Offline Offline

Posts: 29334



« Reply #7 on: June 18, 2009, 11:10:58 am »

Perhaps the economy, which has put the kibbosh on construction projects throughout the nation, and the world, has caused the cost of materials to go down?  (It certainly torpedoed the value of recyclable materials...wouldn't it have a similar effect on building materials?)

On the other hand, I also heard that we got fed stimulus money to help pay for the Boulder Bridge.  (Which is good b/c the initial 3rd penny sales tax allotment was about half of that required to demo and rebuild the bridge.)

As demand started to slow drastically for plate steel last year, the mills screeched production way, way down and kept the price inflated as long as they could.  They had unprecidented increases in price for the prior year or so.  We are finally starting to see some of the engineered/manufactured equipment systems prices coming down, but it has lagged way behind the drop in scrap price.

Logged

"It has been said that politics is the second oldest profession. I have learned that it bears a striking resemblance to the first” -Ronald Reagan
Pages: [1]   Go Up
  Print  
 
Jump to:  

 
  Hosted by TulsaConnect and Powered by SMF 1.1.21 | SMF © 2015, Simple Machines
 

Mission

 

"TulsaNow's Mission is to help Tulsa become the most vibrant, diverse, sustainable and prosperous city of our size. We achieve this by focusing on the development of Tulsa's distinctive identity and economic growth around a dynamic, urban core, complemented by a constellation of livable, thriving communities."
more...

 

Contact

 

2210 S Main St.
Tulsa, OK 74114
(918) 409-2669
info@tulsanow.org